120MW Relax Wind Park 1
Construction of an onshore wind farm in the Margonin region of northwest Poland.
EDP bought the Relax Wind Parks portfolio - which totals more than 1GW in potential developments - in 2007.
Maintenance work will be carried out by Gamesa Wind Polska.
The Relax 1 project comprises two sites:
- Margonin Zachód wind farm - 11 wind turbines of a capacity 2MW each and total capacity 22MW already installed
- Margonin Wschód wind farm - 49 wind turbines of 2MW capacity each and a total capacity of 98MW already installed
The project is a first stage of a larger development planned by EDP in the same area. The further development of the project assumes:
- Installation of 60 wind turbines of 1.5MW each (i.e. 90MW in total) in the Golancz commune
- Installation of five 1.5MW turbines with a total capacity of 7.5MW in Golancz commune
- Installation of 31 wind turbines in the Wagrowiec commune
At completion of these projects, the wind farms operated by the company in the area will have a total capacity of 240MW.
Latest Event: Approval